Course Update

It is no surprise that the recent snow storm that dumped over a foot in our area has slowed our bunker project down. I can say that they did a great job of working over this past weekend to Wednesday to almost having #8 complete with the gravel install and partial #7 fairway bunker. We also have started our annual painting of the shop floor again and we keep trying different coatings to see which one will hold up best for the traffic. Our second phase of tree plantings is under way and this will take us a little longer as compared to the first phase. They are being very careful using mats to get to the area with out disrupting the grass or creating ruts from the heavy weight.

#9 right fairway bunker

#9 back green side bunker

#9 right green side bunker

#8 shaping the front green side bunker

#7 fairway bunker

#8 right side fairway bunkers, small pot bunker has been
filled in.

Tree company slowly making there way to #3,
one mat at a time.

Approximately 15 Trees will go in on the left side to
screen the homes on #3 Tee box.

This is the mechanics office complete, next week we will
work the bathrooms and then the main bay.