Tuesday, December 17, 2013

December 17th Course Update

The bunker construction crew returned yesterday to catch back up where they had left off. Very quickly they roughed in the drainage in the bunkers on #11 and this hole will be ready for the polymer. The company that sprays the polymer will be here tomorrow to spray holes 15,16,17 and 11. Once that is complete and cured the other team will return to continue to add the sand. This leaves us with 18 and 10 to complete and puts us just shy of attaining our goal to be done with the back side before the New Year, not bad concerning the weather we have had.

The Lakewood logo beech tree has been planted and looking great in the parking lot.

15 fairway bunker looking good

#11 right side bunker getting closer

#11 left side bunker 

#11 left side bunker another view

#18 green side left bunker, removing the old sand.

Old bunker sand being top dressed into the rough, its been
a bad area to grow grass, this should help water infiltration.


Tree spade prep

Lakewood logo Beech Tree is back