Thursday, December 13, 2012

#3 Green, Day 3

Things are going well on this project but I wont lie its a tremendous headache to keep the sand from falling into the gravel trench. A positive note on this is we have perfected our excavating strategies to limit the cave in's. The first drain line is installed and being back filled with gravel and sand. After this we will move to the next install on the right side of the green working our way down the line. At some point the mainline will be removed and the trench bottom will be worked to have the fall that is needed. At this point part of the reason we have water holding in front of the green is there is a low point in the trench. 

This is the drainage as built's for the green, The lines marked in
blue are the lines that should be there from the map but are absent.
These are the lines we will install to make correct.

Dotted line on left is our first install

Cleaning out the trench

Pipe install

Back filling with gravel and sand to follow.